|
TABLE OF CONTENTS
STATE MINIMUM STANDARDS AND
SPECIFICATIONS
Source: Virginia Erosion and Sediment Control Handbook
Third Edition 1992
TURBIDITY
CURTAIN
.Page 2
Definition Purpose
Conditions where Practice Applies
PLANNING
CONSIDERATIONS
..Page 2
DESIGN
CRITERIA
.
Page
3
1. Type I Configuration
2. Type II Configuration
3. Type III Configuration
4. Extend Turbidity Curtains
5. "Gap" Allowance for Tidal, Wind, or Wave Action
6. Turbidity Curtain Depth
7. Turbidity Curtain Location
8. Sizing / Measuring
9. Joints
10. Span Maximum
11. End Extensions
12. "Flow-through" Medium
13. Turbidity Curtain Alignments
CONSTRUCTION
SPECIFICATIONS
..Page 4
Materials
1. Barriers
2. Curtain Fabric
3. Fabric Seams
4. Flotation Devices
5. Load Lines
6. External Anchors
7. Bottom Anchors
INSTALLATION
..Page
5
Type I installation - Calm water of lakes or ponds
Type II and Type III installations - Rivers or other moving waters
REMOVAL
.
.
..Page
6
MAINTENANCE
.
.........
Page
6
PHYSICAL
PROPERTIES OF TURBIDITY CURTAIN...........
Page 7
FABRIC OPTIONS AVAILABLE
.
..
..
Page
7
Virginia Department of Conservation and Recreation Division of Soil
and Water Conservation
TURBIDITY
CURTAIN
Definition
A floating geotextile material placed so as to minimize sediment transport
from a disturbed area adjacent to or within a body of water.
Purpose
To provide sedimentation protection for a watercourse from up-slope land
disturbance, or from dredging or filling within the watercourse.
Conditions Where Practice Applies
Applicable to non-tidal and tidal watercourses where intrusion into the
watercourse by construction activities and subsequent sediment movement is
unavoidable.
PLANNING
CONSIDERATIONS
Soil loss into a watercourse results in long-term suspension of sediment.
In time, the suspended sediment may travel long distances and affect
widespread areas. A turbidity curtain is designed to deflect and contain
sediment within a limited area and provide enough residence time so that
soil particles will fall out of suspension and not travel to other areas.
Turbidity curtain types must be selected based on flow conditions within
the water body, be it a flowing channel lake pond, or tidal watercourse.
The specifications contained within this practice pertain to minimal and
moderate flow conditions where the velocity of flow (current) may reach 5
feet per second (approximately three knots). Where there are greater flow
velocities or currents, a qualified engineer and the manufacturer should
be consulted.
Consideration must also be given to the
direction of water movement in channel flow situations. Turbidity curtains
are not designed to act as water impoundment dams and cannot be expected
to stop the flow of a significant volume of water. They are designed and
installed to trap sediment, not to halt the movement of water itself. In
most situations, turbidity curtains should not be installed across channel
flows.
In tidal or moving water conditions, provisions must be made to allow the
volume of water contained within the curtain to change. Since the bottom
of the curtain is weighted and external anchors are frequently added, the
volume of water contained within the curtain will be much greater at high
tide then at low tide and measures must be taken to prevent the curtain
from submerging. To allow the slack of the curtain to rise and fall, water
must be allowed to flow through the curtain while allowing it to remain in
approximately the same spot and to maintain its shape. Normally, this is
achieved by constructing part of the curtain from a heavy woven filter
fabric. The fabric allows the water to pass through the curtain, but
retains the sediment pollutants and consideration should be given to the
quality of water that must pass through the fabric, and sediment particle
size, when specifying fabric permeability.
Sediment, which has been deflected and settled out by the curtain, may be
removed if so directed by the on-site inspectors or Plan Approving
Authority. However, consideration must be given to the probable outcome of
the procedure: will it create more of a sediment problem by re-suspending
particles and by accidental dumping of the material by the equipment
involved? In light of such possibility, it is recommended that the soil
particles be trapped by a turbidity curtain be removed only if there has
been a significant change in the original contours of the of the affected
area in the watercourse. Regardless of the decision made, soil particles
should always be allowed to settle for a minimum of 6 to 12 hours prior to
the removal of the equipment, or prior to their removal by equipment, or
prior to removal of a turbidity curtain.
It is imperative that the intended function of the other controls in this
chapter, to keep sediment out of the watercourse, be the strategy used in
every erosion control plan. However, when proximity to the watercourse
makes successful mitigating sediment loss impossible, the use of the
turbidity curtain during land disturbance is essential.
DESIGN
CRITERIA
1. Type I configuration (see page 8) should be used in protected areas
where there is no current and the area is sheltered from wind and waves.
2. Type II configuration (see page 8)
should be used in areas where there may be slow to moderate running
current (up to 2 knots or 3.5 feet per second) and/or wind and wave action
which can affect the curtain.
3. Type III configuration (see page 8)
should be used in areas where considerable current (up to 3 knots or 5
feet per second) may be present, where tidal action may be present, and/or
where the curtain is potentially subject to wind and wave action.
4. Turbidity curtains should extend the
entire depth of the watercourse whenever the watercourse in question is
not subject to tidal action and/or significant wind and wave forces.
5. In tidal and/or wind and wave action
situations, the curtain should never be so
long as to touch the bottom. A minimum 1-foot "gap" should exist
between the ballast and the bottom of the skirt at "mean low
water." Movement of the lower skirt over the bottom due to tidal
reverses, or wind and wave action on the flotation system, may fan and
stir sediments already settled out.
6. In tidal and/or wind and wave action
situations, it is seldom practical to extend a turbidity curtain depth
lower than 10 to 12 feet below the surface, even in deep water. Curtains
which are installed deeper than this will be subject to very large loads,
with consequent strain on curtain materials and the mooring system. In
addition, a curtain installed in such a manner can "billow up"
towards the surface under the pressure of the moving water, which will
result in an effective depth significantly less than the skirt depth.
7. Turbidity curtains should be located
parallel to the direction of flow of a moving body of water. Turbidity
curtains should not be placed across the main flow of a significantly
moving body of water.
8. When sizing the length of the floating
curtain, allow an additional 10-20% variance in the straight-line
measurements. This will allow for measuring errors, make installing
easier, and reduce stress from potential wave action during high winds.
9. An attempt should be made to avoid an
excessive number of joints in the curtain; a minimum continuous span of 50
feet between joints is a good "rule of thumb".
10. For stability reasons, a maximum span
of 100 feet between joints (anchors or stake locations) is also a good
rule to follow.
11. The ends of the curtain, both floating
upper and weighted lower, should extend well up into the shoreline,
especially if high water conditions are expected. The ends should be
secured firmly to the shoreline (preferably to rigid bodies such as trees
or piles) to enclose fully the area where sediment may enter the water.
12. When there is a specific need to extend
the curtain to the bottom of the watercourse in tidal or moving water
conditions, a heavy woven pervious filter fabric may be substituted for
the normally recommended impervious geotextile. This creates a
"flow-through" medium, which significantly reduces the pressure
on the curtain and keeps it in the same relative location and shape during
the rise and fall of tidal waters.
13. Typical alignments of turbidity
curtains can be seen on page 9. The number and spacing of external anchors
may vary depending on current velocities and potential wind and wave
action; Parker Systems recommendations should be followed.
CONSTRUCTION
SPECIFICATIONS
Materials
1. Barriers should be a bright color (yellow or "international"
orange are recommended) that will attract the attention of nearby boaters.
2. The curtain fabric must meet the minimum
requirements noted in table on page 7.
3. Seams in the fabric shall be either
vulcanized, welded, or sewn, and shall develop the full strength of the
fabric.
4. Flotation devices shall be flexible,
buoyant units, contained in an individual flotation sleeve or collar
attached to the curtain.
Buoyancy provided by the flotation units shall be sufficient to support
the weight of the curtain and maintain a freeboard of at least 3 inches
above the water surface (see page 9).
5. Load lines must be fabricated into the bottom of all floating turbidity
curtains. Type II and Type III must have load lines also fabricated into
the top of the fabric. The top load line shall consist of woven webbing or
vinyl-sheathed steel cable, and shall have break strength in excess of
10,000 pounds. The supplemental (bottom) load line shall consist of a
chain incorporated into the bottom hem of the curtain, with sufficient
weight to serve as ballast to hold the curtain in a vertical position.
Additional anchorage shall be provided as necessary. The load lines shall
have suitable connecting devices which develop the full breaking strength
for connecting to load lines in Type I adjacent sections (see page 8).
6. External anchors may consist of wooden
or metal stakes (2- x 4-inch or 2.5-inch minimum diameter wood, or 1.33
pounds/linear foot steel) when Type I installation is used; when using
type II or Type III installation, bottom anchors must be used.
7. Bottom anchors must be sufficient to
hold the curtain in the same position relative to the bottom of the
watercourse, without interfering with the action of the curtain. The
anchor may dig into the bottom (grappling hook, plow or fluke-type), or
may be weighted (mushroom type), and should be attached to a floating
anchor buoy via an anchor line. The anchor line would then run from the
buoy to the top load line of the curtain. When used with Type III
installation, these lines must contain enough slack to allow the buoy and
curtain to float freely with tidal changes without pulling the buoy or
curtain down, and must be checked regularly to make sure they do not
become entangled with debris. As previously noted, anchor spacing will
vary with current velocity and potential wind and wave action;
manufacturer's recommendations should be followed. See orientation of
external anchors and anchor buoys for tidal installation on page 9.
INSTALLATION
1.In calm waters, such as lakes and ponds (Type I installation) it is
usually sufficient merely to set the curtain end stakes or anchor points
(using anchor buoys if bottom anchors are employed), then tow out the
curtain in the furled condition and attach it to these stakes or anchor
points. Following this, any additional stakes or buoyed anchors required
to maintain the desired location of the curtain may be set, and these
anchor points made fast to the curtain. Only then should the furling lines
be loosened to let the curtain skirt drop. Furling systems are a valuable
option to have included on the curtain for ease of installation and
removal.
2. In rivers or in other moving water (Type
II and Type III installations), it is important to set all the curtain
anchor points. Care must be taken, prior to putting the furled curtain
into the water, to ensure that anchor points are of sufficient holding
power to retain the curtain under the existing current conditions. Again,
anchor buoys should be employed on all anchors to prevent the current from
submerging the flotation at the anchor points. If the moving water into
which the curtain is being installed is tidal and will subject the curtain
to currents in both directions as the tide changes, it is important to
provide anchors on both sides of the curtain for two reasons:
a) Curtain movements will be minimized during tidal current reversals.
b) The curtain will not overrun the anchors and pull them out when the
tide reverses.
Once the anchors are secure, the furled curtain should be secured first to
the anchor point that is farthest upstream, then attached sequentially to
each downstream anchor point in turn until the entire curtain is in
position. At this point, and before unfurling, the "lay" of the
curtain should be assessed and any necessary adjustments made to the
anchors. Finally, when the location is ascertained to be as desired, the
furling lines should be loosened to allow the skirt to drop.
3. Always attach anchor lines to the
flotation device, not to the bottom of the curtain. The anchoring line
attached to the downstream side of the flotation device will provide
support for the curtain. Attaching the anchors to the bottom of the
curtain could cause premature failure of the curtain due to stresses
imparted on its middle section.
4. There is an exception to the rule that
turbidity curtains should not be installed across channel flows; it occurs
when there is a danger of creating a silt build-up in the middle of a
watercourse, thereby blocking access or creating a sand bar. Curtains have
been used effectively in large areas of moving water by forming a very
long sided, sharp "V" to deflect clean water around a work site,
confine a large part of the silt-laden water to the work area inside the
"V" and direct much of the silt toward the shoreline. Care must
be taken, however, not to install the curtain perpendicular to the water
current.
5. See page 9 for typical installation
layouts.
REMOVAL
1. Care should be taken to protect the turbidity curtain skirt from damage
by furling the curtain before it is removed from the water.
2. The site selected to bring the curtain
ashore should be free of sharp rocks, broken cement, debris, etc., so as
to minimize damage when hauling the curtain over the area.
3. If the curtain has a deep skirt and no
furling system, it can further be protected by running a small boat with a
crew installing furling lines along its length before attempting to remove
the curtain from the water.
MAINTENANCE
1.The developer / owner is responsible for maintenance of the filter
curtain for the duration of the project in order to ensure the continuous
protection of the watercourse.
2. Should repairs to the geotextile fabric
become necessary, there are repair kits available from Parker Systems, and
their instructions must be followed to ensure the adequacy of the repair.
3. When the curtain is no longer required,
as determined by the inspector, the curtain and related components must be
removed in such a manner as to minimize turbidity. Remaining sediment must
be sufficiently settled before removing the curtain. Sediment may be
removed and the original depth (or plan elevation) restored. Any spoils
must be taken to an upland area and be stabilized.
PHYSICAL
PROPERTIES OF TURBIDITY CURTAIN FABRIC
| PHYSICAL
PROPERTY |
REQUIREMENT |
| THICKNESS, MILS |
45 |
| WEIGHT/OZ.SQ.YD: |
|
|
TYPE I |
18 |
|
TYPE II |
18 OR 22 |
|
TYPE III |
22 |
| GRAB TENSILE STRENGTH,
LBS. |
300 |
| UV INHIBITOR |
MUST BE INCLUDED |
OPTIONS
AVAILABLE
| Fabrics: |
Upper
Tension Member:
Polyolifin Rope
1/4" Coated Galvanized Cable
5/16" Coated Galvanized Cable |
| Impervious |
Reinforced PVC Coated
14 Oz./Sq. Yd.
18 Oz.
22 Oz. |
Reinforced Alloy Coated
24 Oz./Sq. Yd.
30 Oz.
Reinforced
Urethane Coated
23 Oz./Sq. Yd. |
Lower Tension Members
(Ballast):
1/4" Galvanized Proof Coil Chain
5/16" Galvanized Proof Coil Chain
3/8" Galvanized Proof Coil Chain
Dual ผ" Galvanized Proof Coil
Chains |
Pervious
Geotextile (Woven Polyolifin
Mesh)
Skirt Insert (as required)
Entire Barrier |
Flotation:
Styrofoam: Available in 4" x 4"through 12" x 12"
Rolled Polyolifin Foam with diameters 6"
and up (resistant to oil)
|
Section Connections:
Grommets & Laced
Slotted Tube (PVC Pipe)
Extruded Aluminum
Quick-Latch |
|
When specifying a barrier to prevent silt migration: Due to the many
variables to be considered at a construction site, we recommend that you
consult with our field tested experts to obtain the best possible results.

Click to Enlarge
Top of page
|